下庄水电站首部取水口设计方案比选

发布时间:2018-04-25 00:39

  本文选题:水电站 + 首部取水口 ; 参考:《水电能源科学》2016年01期


【摘要】:为增大下庄水电站进水口引用流量,扩大其装机容量,采用数学模型法对下庄水电站首部取水口3种设计方案进行比选,并结合物理模型研究了推荐方案的可行性。结果表明,方案3首部取水口数模流态良好,流速分布均匀,满足取水口工程要求;二维数学模型模拟取水口三维水流有一定缺陷,但整体流态分布大致相同,对于实际工程仍有一定指导意义。研究结果可作为下庄水电站扩容改造的理论依据。
[Abstract]:In order to increase the intake flow and expand the installed capacity of Xiazhuang Hydropower Station, the mathematical model method is used to compare and select the three design schemes of the first intake of Xiazhuang Hydropower Station, and the feasibility of the recommended scheme is studied in combination with the physical model. The results show that the flow pattern of the first intake of scheme 3 is good and the velocity distribution is uniform, which meets the requirements of the intake engineering, and the two-dimensional mathematical model has some defects in simulating the three-dimensional flow at the intake, but the overall flow pattern distribution is approximately the same. It still has certain guiding significance to the actual project. The results can be used as the theoretical basis for capacity expansion and reconstruction of Xiazhuang Hydropower Station.
【作者单位】: 四川大学水力学与山区河流开发保护国家重点实验室;
【分类号】:TV732

【相似文献】

相关期刊论文 前10条

1 王瑛;;山西省中部引黄工程首部取水枢纽方案比选[J];山西水利;2014年04期

2 李寿乐;;南湖撇洪工程综合治理方案比选[J];湖南水利水电;2009年02期

3 吴坤占;刘克平;孟庆峰;;非线性有限元计算在结构分缝设计中的应用[J];中国水运(下半月);2014年08期

4 韩金超;;松花江堤防蒲鸭河口段建设方案的确定[J];水利科技与经济;2014年06期

5 朱峰,解鹏,文希贤;北方城区段河道综合治理方案比选分析[J];水利技术监督;2005年06期

6 王辉;;京杭运河常州段改线工程进口口门方案比选[J];水利水电科技进展;2005年06期

7 付强;王晓莉;;水利工程的目标规划与方案比选[J];治淮;2007年08期

8 陈来华;潘存鸿;;钱塘江强潮河段江道缩窄治理研究[J];海洋工程;2008年02期

9 黄勇;;双石桥水库大坝整治方案比较[J];内江科技;2010年06期

10 ;[J];;年期



本文编号:1799011

资料下载
论文发表

本文链接:https://www.wllwen.com/kejilunwen/shuiwenshuili/1799011.html


Copyright(c)文论论文网All Rights Reserved | 网站地图 |

版权申明:资料由用户a98fe***提供,本站仅收录摘要或目录,作者需要删除请E-mail邮箱bigeng88@qq.com